Concession Contracts Regulations
Contents |
[edit] Introduction
A concession contract is a contract between a company and a government; or between a contracting authority/utility company and an economic operator/other property owner to operate a business in a particular location.
A ‘contracting authority’ is defined as a ‘state, regional or local authority’ while a utility is defined as an entity that pursues one of the activities listed in Schedule 2.
Payment (or consideration) may come from the contractor exploiting the contractual right to profit from the arrangement or else by exploiting the contract for profit plus a payment from the contracting authority.
Under such contracts, the operating risk of exploiting the contract falls on the contractor, i.e. they must face the vagaries of the market whether connected to demand or supply or both. Any losses incurred by the concessionaire in these respects must be accepted. Furthermore, it is understood from the outset that there is no guarantee they will recoup their investments or the costs involved in operating the concession under normal operating conditions.
A typical example of a concession that might be the subject of a contract is a car park built on local authority-owned land, where the contract will be between the local authority (contracting authority) and the car-park operator. Either of these may involve a transfer of ownership to the contracting authority at some point in the future.
[edit] The Regulations
The Concession Contracts Regulations 2016 (“CCR 2016”) came into force on April 18 for concessions advertised in the Official Journal of the European Union (OJEU) (this may change after the UK leaves the EU). The regulations cover England, Wales and Northern Ireland, and regulate the process of procuring concessions’ contracts, with reference to contracts advertised in the journal by contracting authorities and utilities (e.g water companies power suppliers etc). They do not cover projects started before April 18 2016.2
Regulation 8 of the CCR 2016 suite of regulations stipulates a maximum threshold of €5,225,000. The regulation contains a defined procedure that sets out how to calculate the potential value of the concession. The value is determined by the contracting authority estimating the total amount turned over by the contractor/concessionaire over the contract term by operating the services that are the subject of the contract.
[edit] The two types of concession contract:
- Works concession contract – i.e for the execution, or design and execution, of, and
- Services concession contract—i.e for the provision and management of services (other than the execution of works).
[edit] Arrangements not considered concession contracts include:
- Outsourcing contracts or privatisation;
- Financing works or services e.g a grant;
- If there is a choice for customers between providers delivering the same service;
- A land lease contract;
- Where an economic operator has a right to exploit public domains such as maritime, inland ports or the airport sector as these may involve general conditions for their use without the need to procure specific works and services;
- Granting the right of way covering the use of public immovable property, fixed lines or networks;
- Where no payments are made but the contract is remunerated on the basis of regulated tariffs calculated to cover all costs and investments borne by the concessionaire for providing the service. The concessionaire must be exposed to a potential loss;
- Where the contracting authority or utility relieves the concessionaire of any loss by guaranteeing minimal revenue equal or higher to the investment made and the costs the economic operator has to incur, and
- Where sector-specific regulations eliminate the risk by providing a guarantee to the concessionaire of breaking even in terms of the investments and costs incurred for operating the concession.
The full list of what is not regarded as a concession contract can be found here:
[edit] Related articles on Designing Buildings Wiki
- Back-to-back provisions in construction contacts.
- Collateral warranties.
- Construction manager.
- Contract.
- Design, build, manage contractor.
- Management contract.
- Management contracting - pros and cons.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade contractor.
- Types of contractor.
- Work package contractor.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.